A captive plant saves money only while it keeps its captive status. When a distribution company questions that status, withholds a rebate or levies a surcharge, ENP prepares the case and argues it before the regulator.

Discuss your captive power matter
+91 98269 71771Monday to Saturday, 10 am to 7 pm

What ENP handles

  • Captive status verificationForm V filings and disputes under the 2023 verification regulations, before SLDC and the captive status committee.
  • Additional surchargeChallenging surcharge levied on power from captive and cogeneration plants, and recovering amounts paid.
  • Captive rebatesHV-3 captive consumer rebates and Time of Day rebates withheld by the distribution company.
  • Renewable purchase obligationRPO computation for captive users, including double counting of captive and open access energy.
  • Wheeling and bankingSettlement of surplus energy from captive solar plants and alignment of wheeling agreements.
  • Plant records and meteringGeneration records, meter data and joint readings that the verification rests on.

How an engagement runs

  1. Review of bills, orders and recordsWe establish what the distribution company or the other side has levied, withheld or claimed, and why.
  2. Representation to the utilityMany disputes close at this stage with a reasoned letter that cites the regulations.
  3. Petition before the forumWhere needed, a petition to the state commission, CERC or the Electricity Ombudsman, or an appeal to APTEL.
  4. Hearing and complianceMr. Ajay Porwal appears at the hearing, and we follow the order through to refund, revised bills or compliance.
Has your rebate been withheld or a surcharge levied?

Send the bill or the utility's letter. We will tell you where you stand.

Book a consultation

Orders on record

Each case number can be checked on the issuing commission's website.

Order dateForumMatter
24 Sep 2026MPERC Captive Status CommitteeRepresentation under Regulation 9UltraTech Cement: captive status verification

Distribution company directed to verify Form V from generation records, without insisting on ABT meter data.

15 Jul 2026MPERCPetition 05/2026Porwal Auto Components: refund of additional surcharge

Levy on a captive user held not sustainable; refund with carrying cost and outstanding demand withdrawn.

5 May 2025MPERCReview Petition 03/2025Prism Cement: renewable purchase obligation

Double counting of captive energy accepted and the RPO recomputed.

19 Jul 2024APTELAppeal 241/2021Porwal Auto Components: additional surcharge before APTEL

Captive users not liable for additional surcharge; refund ordered.

11 Sep 2023MPERCPetition 19/2023Tirupati Starch: additional surcharge on captive power

Surcharge held not leviable; demand withdrawn and rebates restored.

6 Sep 2023MPERCPetition 16/2023Birla Corporation: captive power plant rebate

Distribution company directed to verify CPP status and allow the rebate.

29 Jun 2021MPERCPetition 66/2020Porwal Auto Components: Time of Day rebate

Rebate continues after registration under Regulation 12D.

Related engineering work

ENP also engineers captive plants: the 30 MWp solar park planned by Porwal Auto Components at Karodia, Ujjain, and project management for GAIL’s captive solar plant at Vijaipur. See Project Management Consultancy.

Have a dispute with your distribution company, a captive status question or a solar project to plan?

Share the bill, the order or the project brief. You will hear back within 7 days, sooner when the matter is urgent.

Book a consultationor speak to us now+91 98269 71771Monday to Saturday, 10 am to 7 pm