What ENP handles
- Feasibility and DPRTechno-feasibility reports and DPRs for captive and utility solar.
- EPC tender and bid evaluationTender documents, bid evaluation and appointment of the contractor.
- Drawing approval and quality plansReview of the contractor's drawings, data sheets and quality plans.
- Construction supervisionSupervision on site so the plant is built to the design.
- Testing and commissioningInspection of materials and witnessing of the tests that prove the plant.
- Performance monitoringCUF and PR monitoring, and award of O&M contracts.
How an engagement runs
- Feasibility and DPRLoad, site and regulatory position assessed; a feasibility report or DPR the owner can take a decision on.
- Design and tenderDesign, estimates and EPC tender documents; bid evaluation and appointment of the contractor.
- Drawing approval and quality plansThe contractor's drawings, data sheets and quality plans checked against the design.
- Supervision, testing and commissioningSite supervision, inspection of materials, witnessing of tests, and commissioning.
- Handover and performanceHandover to the owner, with CUF and PR monitoring where the owner needs it.
Planning a solar plant or a line?
Book a consultationTalk to us before you tender. We reply within 7 days.
Projects
- Solar PMCGAIL Vijaipur: 1.8 MWp ground mounted solar PMCPMC for a 1.8 MWp captive ground mounted solar plant: design, construction supervision and commissioning.
- Solar PMCGAIL Pata: 2.64 MWp rooftop solar PMCFull PMC for rooftop solar in two phases, with a 10 year O&M contract and CUF and PR monitoring.
- Solar PMC and erectionFreewings Power and Infra: 6 MWp solar, Ujjain6 MWp solar plant with a 33 kV substation, with power sold through the exchange under open access.
- Captive solarPorwal Auto Components: captive solar plants, UjjainProject Management Consultant and Techno-legal Consultant for the captive solar plants wheeling power to the Pithampur works.
- Solar DPR and PMCIndore Smart City: 100 MW Jalood DPR and 2.059 MW solar PMCDPR for a 100 MW solar plant at Jalood, and PMC for a 2.059 MW ground mounted plant.
- Rooftop solarPrem Textiles: 1 MWp rooftop solar, BarwahFeasibility study and PMC for a 1 MWp rooftop plant, with a study of the existing distribution system.
- HV and EHVNarmada-Gambhir Link: HV and EHV power supplySurvey of HV and EHV cables and lines, and 132 kV pump station connections for the Narmada-Malwa Gambhir Link.
Ongoing
- Oil India Ltd: PMC, 1.3 MWp captive solar plant, Jaisalmer (since 2025)
- Indraprastha Gas Ltd: EPC bid process management and PMC, 28 MWp solar, Delhi region (since 2025)
- GAIL (India) Ltd, Visakhapatnam: PMC, 500 kW rooftop and ground solar (since 2024)
- HPCL Renewable and Green Energy Ltd: PMC, 538 kWp net metering solar, Karnataka (since 2024)