Birla Corporation: captive power plant rebate

Petition no.
Petition 16/2023
Forum
Madhya Pradesh Electricity Regulatory Commission (MPERC)
Order date
6 September 2023

Subject

Captive power plant rebate of Birla Corporation Ltd, Satna Cement Works, for FY 2021-22 and 2022-23.

Result

Distribution company directed to verify CPP status and comply with the tariff orders within one month.

Official copy

The full order is published by MPERC and can be found on its website by the petition number above.

Facing a similar matter?

Send the order, bill or letter you have received.

Book a consultation

Summary prepared by Electricity No Problem from the published order. The official order is the authoritative text.

Have a dispute with your distribution company, a captive status question or a solar project to plan?

Share the bill, the order or the project brief. You will hear back within 7 days, sooner when the matter is urgent.

Book a consultationor speak to us now+91 98269 71771Monday to Saturday, 10 am to 7 pm